Financing Big Projects and Infrastructure
Tunnels, rail lines, power plants and pipelines are rarely paid for with one check. This page explains the main tools (project debt, public bonds, federal loans, tax credits, concessions) and what went right and wrong in real deals.
- Project finance basics: the SPV, non-recourse debt and coverage ratios
- Public finance: municipal bonds and federal programs
- Public private partnerships: how risk gets transferred (and sometimes does not)
- Energy and industrial projects: tax equity, transferability, DOE loans and offtake
- Project examples: Brightline, Vegas Loop, Gateway and the Channel Tunnel
- Why costs and financing interact
- Practical: reading a bond official statement on EMMA, and where to learn more
- Videos
- Glossary
- Further reading
- Sources
- $4.5 trillionUS municipal bonds outstanding, as of 2Q 2026 (SIFMA) [1]
- $949 millionTIFIA loan on the $2.3 billion I-4 Ultimate project in Florida, closed 2014 [5]
- $16 billionTotal cost of the Hudson Tunnel Project, split 70/30 between USDOT and local partners (2024) [15]
- 44.7%Average rail cost overrun in a 258-project transport study (Flyvbjerg, Holm and Buhl, 2002) [17]
- $1.4 billionCost growth on Maryland's Purple Line design and construction ($2 billion to $3.4 billion), per a 2022 report [8]
Project finance basics: the SPV, non-recourse debt and coverage ratios
Most large infrastructure is not financed against the balance sheet of a big company. Instead the sponsors set up a special purpose vehicle (SPV), a company that is legally and financially separate from them and that owns only the project. Lenders look mainly to the project's own cash flows for repayment. If the project fails, they can reach the SPV's assets but not the sponsors' other assets, which is what non-recourse means in practice 21.
Lenders test whether that cash flow is enough using ratios. The debt service coverage ratio (DSCR) divides the cash available for debt service in a period by the debt payments due in that period. Lenders also look at a loan life coverage ratio over the whole loan. Acceptable levels depend on how well the risks are controlled, including capped construction costs, timely completion, performance to specification and a long-term revenue contract 21. Debt to equity matters too. The more debt the SPV carries, the thinner the cushion, and the more a small revenue miss can threaten repayment.
Construction risk and operating risk are priced very differently. During construction nothing earns revenue, so lenders want a fixed-price, date-certain design-build or engineering and construction contract with a creditworthy contractor. That contract caps overrun exposure and supports liquidated damages and performance security 21. Once the asset operates, the main risks shift to demand, operating cost and maintenance. Projects with a contracted revenue stream (a power purchase agreement or a government availability payment) carry less operating risk than projects that depend on traffic or ridership.
Illustrative example (invented numbers, not data). Suppose an SPV builds a $100 million facility with $70 million of debt and $30 million of equity, a 70/30 split. The debt is a level-payment loan over 20 years at 6 percent, so the annual payment is about $6.1 million. If the project earns $8 million a year of cash available for debt service, DSCR is about 1.31. If revenue falls 20 percent to $6.4 million, DSCR drops to about 1.05, close to the point where the lender can no longer be paid on time. This is why lenders ask for a cushion, often well above 1.0, and why they study the downside case more than the base case.
Illustrative interest during construction. If the same $70 million were drawn evenly over a three year build at 6 percent, simple interest on the average balance would be roughly $6.3 million before the project earns anything. One extra year of delay with the full balance outstanding adds about $4.2 million of interest, plus any extra cost of the delay itself. The money has to come from somewhere, usually more debt or equity. For anything this size, get a project finance lawyer and an independent financial advisor involved early.
Public finance: municipal bonds and federal programs
State and local governments finance a large share of US infrastructure by selling municipal bonds. SIFMA reports about $4.5 trillion of municipal bonds outstanding as of the second quarter of 2026, up 4.8 percent from a year earlier. It also reports $521.0 billion of issuance through October 2026 1. Issuers range from states to small districts, which is why disclosure through the MSRB's EMMA system matters (see the last section).
The MSRB describes three basic types. General obligation (GO) bonds are secured by the issuer's broad taxing power and the full faith and credit pledge. Revenue bonds are repaid from income from a specific project, such as toll roads, bridges, airports, utilities, colleges or hospitals. Private activity bonds are a type of revenue bond issued for private entities that cannot issue tax-exempt debt themselves. A public entity acts as conduit issuer, but the private borrower is responsible for paying interest and principal 2. Whether the interest is actually tax-exempt depends on federal tax rules and on volume limits, so issuers rely on bond counsel.
Federal money comes as grants and as loans. The Federal Transit Administration's Capital Investment Grants program funds three categories under 49 U.S.C. 5309: new fixed guideway projects (often called New Starts), Small Starts and Core Capacity. A Small Start is a project with federal assistance under $150 million and total net capital cost under $400 million. For a new fixed guideway project, the statute caps the grant at 80 percent of net capital project cost, and a full funding grant agreement may not include more than 60 percent from Section 5309 funds 4. Check transit.dot.gov for current FTA guidance and project ratings.
The Build America Bureau at USDOT runs the TIFIA and RRIF credit programs. Under the TIFIA statute, a secured loan may not exceed 49 percent of reasonably anticipated eligible project costs. If the loan does not receive an investment-grade rating, it also may not exceed the amount of the senior project obligations. The interest rate must be at least the Treasury yield for a similar maturity. Final maturity is generally the lesser of 35 years after substantial completion or the asset's useful life, with longer terms possible for very long-lived assets 3. TIFIA is a loan, not a grant, so the project still needs its own repayment source. RRIF is the Bureau's rail loan program. The Hudson Tunnel Project was approved for three RRIF loans totaling $4.1 billion, described as carrying below-market interest rates 15. Check the Bureau's own pages for current terms.
Public private partnerships: how risk gets transferred (and sometimes does not)
In a public private partnership (P3), a government signs a long contract with a private consortium that designs, builds, finances, operates and maintains an asset, often called DBFOM. The two main payment models differ in who carries demand risk. In a toll concession the private partner collects the tolls and bears traffic risk. In an availability payment deal the government pays the partner as long as the asset is open and meets performance standards, so the partner bears construction, performance and maintenance risk but not traffic risk.
I-4 Ultimate in Orlando is an availability payment case. Florida DOT awarded a 40 year concession to I-4 Mobility Partners, led by Skanska and John Laing, to reconstruct 21 miles of I-4 in Orange and Seminole counties. The project was valued at $2.3 billion, with commercial and financial close in September 2014. Nossaman, a law firm that advised the state, described it as the largest greenfield availability payment deal in the US at the time. It used a $949 million TIFIA loan, which the firm called the largest in the program's history to that point. Florida secured a $2 billion private activity bond allocation, but the final financing structure did not include PAB financing 5. The lesson is that a financing plan can change late, and that the federal loan was a core part of the capital stack.
Maryland's Purple Line shows how a P3 can strain. The state signed a P3 for a light rail line with Purple Line Transit Partners, whose partners were Meridiam, Star America and Fluor 6. A Fluor-led team was the builder 7. A 2022 report said the design and construction cost rose from $2 billion to $3.4 billion, long-term costs rose from $5.6 billion to $9.3 billion, and service slipped from the original spring 2022 target to late 2026 8. The date slipped again later. In March 2024 the state and the concessionaire sought approval to extend the contractual service deadline to winter 2027, with up to $425 million in added compensation to the concessionaire 22. Check the Maryland Transit Administration for the current date. The original builders withdrew in October 2020 after a dispute over delays and cost overruns 7. The state agreed to a $250 million settlement, and Fluor exited the partnership while Meridiam and Star America remained 6. Maryland's annual payments to the concessionaire were reported to rise from an average of $154 million to $240 million, and the increase covered higher construction costs, the settlement and higher expected debt service 7. Delays also raise financing costs, a topic covered below.
Takeaways. A P3 does not make a project cheaper by itself. It moves some risks to the private side in exchange for a price, and a government still pays in the end through tolls or availability payments. Whether the deal is good value depends on risk allocation, procurement quality and how disputes are handled. Change-order terms and the credit of the consortium deserve careful review. The press and law firm sources cited here do not cover full contract terms, so read the primary documents for any specific deal.
Energy and industrial projects: tax equity, transferability, DOE loans and offtake
Energy projects are usually financed against a contracted revenue stream, called an offtake contract. A power purchase agreement with a creditworthy buyer lets lenders model cash flows, because the price and volume are fixed for years. Lenders to these projects often ask for the same things as in any project finance deal: a fixed-price construction contract, a coverage ratio cushion and a long-term revenue contract 21. Merchant projects with no offtake are much harder to finance with non-recourse debt.
Federal clean energy tax credits add another layer. Before 2022, developers typically needed tax equity, an investor with enough tax liability to use credits and depreciation. In a common partnership flip, the investor takes most of the credits and tax losses until it reaches a target return, then its share drops 11. Since the Inflation Reduction Act, section 6418 lets owners sell many credits for cash to an unrelated taxpayer. The buyer must pay cash, a credit can be sold only once, and sellers do not have to report the sale proceeds as income 11. The same source noted that wind and solar credits were then trading mostly at 90 to 92 cents per dollar of credit 11. That is a market report from early 2023, not a current price, so check recent market surveys.
The One Big Beautiful Bill Act, enacted July 4, 2025, changed the credit landscape but kept transferability. Law firm summaries from Kirkland and Sidley both report that the Act preserves transfers under section 6418 while barring transfers to specified foreign entities 910. Sidley adds that the direct-pay option was retained 10. For wind and solar, the section 45Y and 48E credits end unless construction began by July 4, 2026, or the facility is placed in service by December 31, 2027 9. The Act also adds foreign entity of concern restrictions. A material assistance test applies to projects that begin construction after 2025. For section 45Y and 48E generating facilities, the required cost ratio is 40 percent for construction starting in 2026 and rises to 60 percent for 2030 and later, with higher thresholds for energy storage 910. The July 4, 2026 start-of-construction date has now passed, so wind and solar projects that did not begin construction by then face the 2027 placed-in-service cutoff 10. What counts as beginning construction is set by Treasury guidance, so read the statute and current guidance or ask tax counsel.
The Department of Energy's Loan Programs Office (LPO) is another source of long-term debt. Holland and Knight report that the 2025 Act rescinded unobligated Inflation Reduction Act loan commitment authority for several LPO categories and replaced the section 1706 program with Energy Dominance Financing under section 50403. It broadened eligibility to cover more of the energy and critical minerals supply chain, removed an emissions-reduction requirement for fossil projects, and provided $1 billion in new appropriations through fiscal 2028 12. LPO keeps authority already committed through conditional commitments or closed loans 12. New awards depend on the administration's priorities, and federal loan applications involve extensive diligence and documentation.
Project examples: Brightline, Vegas Loop, Gateway and the Channel Tunnel
Brightline Florida is the best-known privately owned passenger rail effort in the US, and its debt has run into trouble. Its financing includes $2.2 billion of Series 2024 tax-exempt revenue bonds issued through the Florida Development Finance Corporation, a conduit issuer that lent the proceeds to Brightline Trains Florida LLC. About $1.13 billion of the private activity bonds carry a financial guaranty from Assured Guaranty. In May 2025 KBRA affirmed the bonds at BBB but revised its outlook to negative, citing ridership underperformance, higher than expected operating expenses and capacity constraints 13. Further downgrades followed. On October 2, 2026, KBRA cut the bonds to C from CCC+ after Brightline Florida signed a restructuring support agreement that defers three interest payments without reducing principal. Certain non-operating parent entities filed for Chapter 11 on September 24, 2026, while the operating company did not file 23. The case shows both sides of private activity bonds: access to tax-exempt debt, and exposure to ridership risk that falls on investors when forecasts are missed. The restructuring was still in progress at the time of writing, so check current reports.
The Boring Company's Vegas Loop has been presented as privately funded, with a franchise from local government. Clark County commissioners gave initial approval in October 2021 to a special use permit and a franchise agreement that would last 50 years. The company said it would pay for the tunnels, and county officials reiterated that. The planned expansion was described as a 29 mile route with 51 stations, beyond the then-current 1.7 mile system, and a separate agreement with the city of Las Vegas was still needed 14. A franchise is a right to operate, not a subsidy, so the company carries construction and ridership risk. These figures are from 2021 and the plans have changed since, so check current county records. The useful point for a founder is that the permit and franchise mattered as much as the engineering.
The Hudson Tunnel Project, part of the Gateway program, is the opposite model: mostly public money. A July 2024 report said the $16 billion project cost would be split 70/30 between USDOT and local partners (New York, New Jersey and the Port Authority). Federal support of about $12 billion included close to $6.9 billion from the FTA Capital Investment Grants program, described as the largest grant ever signed by FTA, and three RRIF loans totaling $4.1 billion 15. Loans have to be repaid, so even a heavily federal project needs a local funding plan. Federal money is also exposed to political risk. USDOT suspended payments on September 30, 2025. A court ordered funds released in February 2026, and on June 29, 2026 a federal judge vacated the suspension and permanently barred USDOT from relying on it. USDOT had not said whether it would appeal when that ruling was reported 24. Check current status before relying on any funding plan.
The Channel Tunnel is the classic cautionary tale of private finance for a mega project. Eurotunnel went public in 1987, and its prospectus said a 10 percent allowance would be reasonable for unforeseen construction cost impacts. Flyvbjerg and coauthors note that actual costs ended up higher by a factor of two compared with forecasts 17. By 2006 the operator was warning of serious financial straits with nearly $11 billion of debt. It was in restructuring talks, creditors might have taken over management, and the chairman wanted most of the debt written off 18. The tunnel was built and runs, so the failure was in the financing and forecasts, not the engineering.
Why costs and financing interact
Financing is not separate from construction cost. Every month of delay adds interest on borrowed money, extends the period before revenue starts, and can trigger penalties, renegotiations and legal fees. The Purple Line example above included higher expected debt service as one reason the concession price rose 7. The Channel Tunnel's operator was still seeking a debt restructuring more than a decade after opening 18. In both, cost and schedule problems turned into financing problems.
Bent Flyvbjerg and coauthors studied 258 transportation infrastructure projects worth US$90 billion and concluded that cost estimates used to decide whether to build are highly and systematically misleading, and that underestimation is best explained by strategic misrepresentation rather than error 16. Average overruns in constant prices were 44.7 percent for rail, 33.8 percent for fixed links (bridges and tunnels) and 20.4 percent for roads 17. The study is from 2002, and projects in the sample span many decades, so use it as a warning about estimating, not as a forecast for your project.
The NYU Marron Institute's Transit Costs Project compares urban rail projects across countries to explain why some cost far more than others. Its database spans more than 50 countries and over 11,000 km of urban rail built since the late 1990s, and it frames its question as why New York projects cost 20 times more per kilometer than Seoul 19. Cost comparisons depend on the dataset, the year and what is counted, so cite the specific dataset when you use its numbers.
Practical implications for a project sponsor. Budget a contingency that reflects the base rate of overruns, not a best case. Model financing under delay, including interest during construction and the cost of extending commitments. Ask who bears each risk in writing. Prefer fixed-price, date-certain construction contracts where the contractor can actually stand behind them 21. And be skeptical of any single cost number from a promoter, including yours.
Practical: reading a bond official statement on EMMA, and where to learn more
The Municipal Securities Rulemaking Board's EMMA system (emma.msrb.org) is the free public library for municipal bond documents. An official statement is the disclosure document for a new bond offering, and Fidelity's guide notes it summarizes the issuer, includes recent financial statements, and describes the bonds and use of proceeds 20.
A reading order that works. Start with the summary on the first page or two, which gives the size of the deal and the underwriters. Then use the table of contents to find the terms of the bonds (maturities, coupons and call features), the purpose of the issue, the sources of payment and security (full faith and credit or specific revenues), ratings, tax exemption and risk factors. Then read the financial statements and legal opinions 20. For a revenue bond, spend the most time on the sources of payment, the rate covenant and the debt service reserve. For a GO bond, spend time on the tax base and existing debt.
Remember that an official statement is a snapshot from when the bond was issued. Fidelity advises pairing it with continuing disclosure and material event notices posted after issuance 20. Brightline is an example. Its 2024 bonds were downgraded several times within about two years of issuance, which no offering document could show 1323.
Where to learn more. Read Flyvbjerg's paper on cost underestimation, the Transit Costs Project, and a project finance primer. Practice on a real deal by pulling one revenue bond official statement and one GO bond official statement and comparing their security sections. If you are building something real, talk to a project finance lawyer, bond counsel, and a tax advisor before you sign anything. This page is general information, not legal, tax or investment advice.
This guide is general information, not legal, tax or investment advice. Rules and figures change. Check the linked sources and talk to a qualified professional before acting.
Videos and podcasts
- Bent Flyvbjerg on Megaprojects 05/25/2015EconTalk · 2020 · 1:04:40Bent Flyvbjerg, Russ Roberts. Flyvbjerg on megaproject cost overruns and why forecasts fail. Foundational research interview, older examples.
- Jigar Shah on the Pathway to Clean, Cheap, and Abundant Energy | Odd LotsBloomberg Podcasts · 2023 · 1:02:55Jigar Shah. Shah on Odd Lots discusses financing clean energy and what LPO does. Long interview with the program head as primary source.
- Financing U.S. Decarbonization: A Conversation with Jigar ShahCenter for Strategic & International Studies · 2023 · 40:29Jigar Shah. CSIS conversation with the LPO director on financing decarbonization and loan program design. Policy audience, reflects the Biden era program.
- How Big Things Get Done: a conversation with Professor Bent FlyvbjergSydney Executive Plus · 2023 · 55:47Bent Flyvbjerg. Flyvbjerg discusses why large projects fail and what planning habits help, drawing on his megaproject database. University executive education conversation.
- Introduction to the Build America BureauBuild America BureauOfficial introduction to the US DOT Build America Bureau and its financing programs. Promotional overview, US specific.
- TIFIA: FHWA Innovative Finance Video SeriesFederal Highway Administration USDOTFHWA · 2021 · 16:10Federal Highway Administration explainer on TIFIA federal credit loans for transport projects. Official source, practical, US specific.
- Duane Callender (TIFIA Credit Program) interviewInternational Transport Forum · 2013 · 2:40Duane Callender. Interview with the head of the US TIFIA credit program on how federal loans support transport projects. Practitioner view, international forum audience.
- How Brightline Plans To Bring High-Speed Rail To The U.S.CNBC · 2023 · 16:22CNBC report on Brightline's plan for private high-speed rail financing. News coverage rather than primary source, and later debt troubles are not covered.
Glossary
- Special purpose vehicle (SPV)
- A company legally and financially separate from its sponsors, created to own one project and borrow against its cash flows.
- Non-recourse debt
- Debt where lenders can look to the project's assets and revenues but not to the sponsors' other assets.
- Debt service coverage ratio (DSCR)
- Cash available for debt service divided by the debt payments due in a period. Lenders want a cushion above 1.0.
- Interest during construction
- Interest that accrues on debt drawn during the build, before the project earns revenue. It is usually funded as part of the project cost.
- General obligation bond
- A municipal bond secured by the issuer's broad taxing power and full faith and credit pledge.
- Revenue bond
- A municipal bond repaid from the income of a specific project such as a toll road, airport or utility.
- Private activity bond
- A type of revenue bond issued through a public conduit issuer for a private borrower, who is responsible for repayment.
- TIFIA
- A federal credit program for transportation projects that provides secured loans, administered by the Build America Bureau.
- Availability payment
- A payment from a government to a private partner for keeping an asset open and meeting performance standards, regardless of traffic.
- Tax equity
- Investment by a party with taxable income who receives tax credits and depreciation from a project, often through a partnership flip.
- Offtake contract
- A long-term agreement by a buyer to purchase a project's output at set terms, which supports lender confidence in future revenue.
- Official statement
- The disclosure document for a municipal bond offering, filed on EMMA, describing the issuer, the bonds, the security and the risks.
Further reading
- Underestimating Costs in Public Works Projects: Error or Lie?, Bent Flyvbjerg, Mette Skamris Holm and Soren Buhl. The 258-project study behind many cost overrun claims, with the Channel Tunnel as a case.
- Transit Costs Project, NYU Marron Institute. Cross-country comparison of urban rail costs and the reasons behind them.
- Mastering the Official Statement, Fidelity. A plain walkthrough of the sections of a municipal bond official statement.
- Core principles of traditional project finance, Gowling WLG. SPVs, non-recourse debt, coverage ratios and construction risk from a law firm's perspective.
- Transferability: Selling Tax Credits, Norton Rose Fulbright (Project Finance NewsWire). How section 6418 credit sales work and how they compare with tax equity (2023, so check for updates).
- How the One Big Beautiful Bill Act Reshapes DOE Loan Programs, Holland & Knight. Explains the shift from IRA-era LPO authority to Energy Dominance Financing.
- US Municipal Bonds Statistics, SIFMA. Current outstanding and issuance data for the municipal market.
- 23 U.S.C. 603, Terms and limitations of credit assistance, Cornell Legal Information Institute. The statutory text for TIFIA loan size, rate and maturity.
Sources
- SIFMA, US Municipal Bonds Statistics
Outstanding (as of 2Q26) $4.5 trillion, +4.8% Y/Y.
Accessed 2026-11-26. - MSRB, Municipal Bond Basics
backed by revenues from specific projects
Accessed 2026-11-26. - Cornell LII, 23 U.S.C. 603 (TIFIA secured loans)
35 years after the date of substantial completion of the project.
Accessed 2026-11-26. - Cornell LII, 49 U.S.C. 5309 (Capital Investment Grants)
the total estimated net capital cost is less than $400,000,000
Accessed 2026-11-26. - Nossaman, Florida's Innovative P3 Success Continues with I-4 Ultimate Project
the ultimate financing structure did not include PAB financing
Accessed 2026-11-26. - Construction Dive, Purple Line contractors reach $250M settlement with Maryland DOT
settles all outstanding financial claims and terminates litigation between the parties
Accessed 2026-11-26. - ENR, State-stalled Maryland light rail P3 will open in 2026, up $1.4B
more than four years past the March 2022 planned operating date
Accessed 2026-11-26. - WJLA, Purple Line project delayed 4.5 years, $1.4B over budget, new report says
won't start running until late 2026
Accessed 2026-11-26. - Kirkland & Ellis, One Big Beautiful Bill Act Brings Big Changes to Green Energy Tax Credits
terminated unless the facility is placed in service on or before December 31, 2027
Accessed 2026-11-26. - Sidley Austin, The One Big Beautiful Bill Act: Navigating the New Energy Landscape
placed in service after December 31, 2027
Accessed 2026-11-26. - Norton Rose Fulbright, Transferability: Selling Tax Credits
A credit can be sold only once
Accessed 2026-11-26. - Holland & Knight, How the One Big Beautiful Bill Act Reshapes DOE Loan Programs
retool, repower, repurpose or replace infrastructure that has ceased operations
Accessed 2026-11-26. - KBRA, Brightline Florida $2.2 Billion Revenue Bonds rating action (May 2025)
ridership underperformance and higher-than-expected operating expenses
Accessed 2026-11-26. - TechCrunch, Elon Musk's Boring Company gets initial OK to expand Loop under Las Vegas Strip
last for 50 years
Accessed 2026-11-26. - Mass Transit, Gateway Development Commission secures full funding for Hudson River tunnel
total $16 billion cost of the project will be split 70/30 between USDOT and the project's local partners
Accessed 2026-11-26. - Flyvbjerg, Holm and Buhl, Underestimating Costs in Public Works Projects: Error or Lie? (abstract, arXiv)
258 transportation infrastructure projects worth US$90 billion
Accessed 2026-11-26. - Flyvbjerg, Holm and Buhl, Underestimating Costs in Public Works Projects: Error or Lie? (full text, arXiv)
Rail projects incur the highest difference between actual and estimated costs with an average of no less than 44.7%
Accessed 2026-11-26. - UPI, Chunnel in financial bind, $11B in debt
serious financial straits
Accessed 2026-11-26. - NYU Marron Institute, Transit Costs Project
Why do transit-infrastructure projects in New York cost 20 times more on a per kilometer basis than in Seoul?
Accessed 2026-11-26. - Fidelity, Mastering the Official Statement
extensive library of historical Official Statements
Accessed 2026-11-26. - Gowling WLG, Core principles of traditional project finance
a fixed-price, date-certain EPC or design-build contract with a creditworthy contractor
Accessed 2026-11-26. - METRO Magazine, Maryland Updates Purple Line Launch Date
will extend the contractual deadline for achieving Revenue Service Availability to Winter 2027
Accessed 2026-11-26. - KBRA, KBRA Downgrades Ratings for Brightline Florida's $2.2 Billion Revenue Bonds to C from CCC+
has not commenced, and is not anticipated to commence, a Chapter 11 case
Accessed 2026-11-26. - ENR, Judge permanently bars USDOT from withholding Gateway grants
permanently bars USDOT from withholding Gateway grants
Accessed 2026-11-26.
More guides
- Startup rounds. Pre-seed to growth: how a round works, SAFEs, term sheets and how VCs decide.
- Deep tech and hardware. Capital heavy companies, milestone rounds, grants, loans and first of a kind plants.
- Foundations and donors. How foundations decide, how major donors are approached, and effective giving.
- Science funding. Federal grants, how to write one, and new models like HHMI, Arc and FROs.
- Nonprofits. Annual funds, major gifts, campaigns and how a new group raises its first dollars.
- Policy and advocacy. Campaign finance law, advocacy funding, ballot measures and issue campaigns.